| | | | | | | | | ITEM 3. Transportation - Administrative Agenda |
|
| | | | | | | | DATE: | May 21, 2019
| DEPARTMENT: | Transportation
| REQUESTER: | Randy Cerchie
| TITLE: | Approve Contract for Design for Littleton Road Widening - Corbett Road to US 41 |
|
| | | | | | | | I. | MOTION REQUESTED | | A) Award Competitive Negotiation Request for Proposal No. CN190114LAC, Design - Littleton Road Widening - Corbett Road to US 41, to David Douglas Associates, Inc., in an amount not to exceed $1,304,848.29.
B) Authorize the Chair to execute the contract documents on behalf of the Board of County Commissioners. |
|
| | | | | | | | II. | ITEM SUMMARY | | Awards contract to David Douglas Associates, Inc., to provide design, permitting, and post design services for the widening of Littleton Road from Corbett Road to US 41, in an amount not to exceed $1,304,848.29. Funding for construction is programmed in FY 2020/21 partially with grant funds. |
|
| | | | | | | | III. | BACKGROUND AND IMPLICATIONS OF ACTION |
|
| | | | | | | | | A) | Board Action and Other History | | | The Lee County Department of Transportation submitted a request to Procurement Management to obtain proposals to contract with a qualified firm to provide design, permitting, and post design services for the widening of Littleton Road from Corbett Road to US 41. On January 8, 2019, the Department of Procurement Management advertised Competitive Negotiation Request for Proposal No. CN190114LAC, Littleton Road Widening - Corbett Road to US 41. On the proposal deadline of February 12, 2019, the Department of Procurement Management received seven proposals. At the first evaluation committee meeting, February 28, 2019, the evaluation committee short-listed four firms to return for presentations and a question and answer session. At the second evaluation committee meeting, March 19, 2019, after the presentations, the committee made the recommendation to award the contract to David Douglas Associates, Inc., following successful negotiations. Staff completed successful negotiations with David Douglas Associates, Inc., resulting in a contract amount not to exceed $1,304,848.29.
On February 21, 2017, the County entered into a contract with AiM Engineering to provide professional services and prepare a roadway alignment study for the Kismet/Littleton Realignment Project. Part of that contract included engineering/environmental analysis and survey for the widening of Littleton Road from Corbett Road to US 41. On January 15, 2019, the Board approved staff's recommended three-lane alternative for the widening. This contract will complete the design and prepare the project for construction. |
|
| | | | | | | | | D) | Analysis | | | The widening of Littleton Road is a Tier One Priority as identified by the Board of County Commissioners. Funding for construction is programmed in FY 2020/21 with a combination of grant funds, gas taxes, and road impact fees. Total project cost is estimated to be $15.3 million. |
|
| | | | | | | | | A) | Current year dollar amount of item:
| $1,304,848.29 | | B) | Is this item approved in the current budget? | Yes | | C) | Is this a revenue or expense item? | Expense | | D) | Is this Discretionary or Mandatory? | Discretionary | | E) | Will this item impact future budgets?
If yes, please include reasons in III(D) above.
| Yes | | F) | Fund: Road Impact Fees
Program: DOT Capital Projects
Project: Littleton Road
Account Strings: 20502838822 | | G) | Fund Type? | Other: Road Impact Fees | | H) | Comments: |
|
REVIEWERS: | Department | Reviewer | Action | Date | Transportation | Turner, Nicole | Approved | 5/13/2019 - 9:08 AM | Transportation | Cerchie, Randy | Approved | 5/13/2019 - 9:35 AM | Budget Services | Henkel, Anne | Approved | 5/13/2019 - 10:00 AM | Budget Services | Winton, Peter | Approved | 5/13/2019 - 10:01 AM | County Attorney | Swindle, Amanda | Approved | 5/13/2019 - 11:37 AM | County Manager | Meurer, Doug | Approved | 5/13/2019 - 11:58 AM |
|
|